Dry and wet tests in progress

Even during the current situation in our company, we are preparing a wastewater treatment plant launch for a bakery near Dunajská Streda. As usual before putting technology in operation, during complex tests we tested correct electrical connection of all machines and their communication with the control system. We also set parameters of measuring devices (level meters, pH and oxygen probes, flow meters, etc.). For a smoother launch of devices, we invited our delivery partners to start the most important machines.

More articles

Read more

Wastewater treatment in big cities: follow Hanoi's example

21.3.2020

Hanoi is planning to build a sewer system to direct the polluted water from the To Lich River to a wastewater treatment plant. What seems to be a...